1. Ticket Details

FieldDescription
Ticket IDAMM-1352
SeverityCritical
CategoryBug
Affected Module / FeatureMMU

2. Issue Description

 Unable to do Data Sync.  In the Production_APL offline MMU- while syncing the data, getting some error related to websphere application/Unexpected end of file from server


3. Root Cause Analysis (RCA)

Use one or more of the following techniques for RCA:


4. Corrective Actions (Fixes for this instance)

ActionOwnerTarget DateStatus
Optimize batch size and implement proper exit conditions to handle large data safelyVanitha2025-07-23Completed
Increase server connection timeout and tune DB pool settingsVanitha2025-07-23Completed

Immediate actions to resolve the issue and restore service.


5. Preventive Actions (To prevent recurrence)

ActionOwnerTarget DateStatus
Review and optimize sync logic in each release cycleVanitha

Schedule data sync to run frequently in smaller batches to prevent large payload failures.Vanitha

Systemic changes, monitoring, alerting, process updates, or automation.


6. Verification of Effectiveness

Monitoring logs and metrics to confirm successful data syncs.

Checking for recurrence of I/O or timeout errors.

Confirming increased connection timeouts are sufficient during large syncs.


7. Lessons Learned

Implement batch processing for large data to avoid timeouts and failures.

Increase connection timeouts and server request handling capacity for heavy operations.

Schedule data syncs more frequently to reduce payload size and risk of failures.


8. CAPA Review & Closure

Reviewed ByDateRemarks