Overview

Module

STOP TB Mobile App (TBMJA)

Release / Version

2.4 – Jira fix version 2.4

Purpose

Define and lock the scope of features/modules/fixes going into v2.4 so BSAs, Delivery Manager, Product and Engineering have one place to review owners, bandwidth and timeline before the sprint begins.

Total Jira tickets

30 (8 Closed, 22 open or in progress)

Proposed release window

Mon 26-Oct to Fri 6-Nov-2026 (10 working days); Sat 7-Nov kept as buffer. Diwali is around Sun 8-Nov.

Last synced with Jira

12-Oct-2026 (see "Changes since last sync" below)

Page status

DRAFT for review – proposed owners, allocation and dates are not confirmed

PRD reference

TBMJA PRD (v186)

Changes since last sync (Jira fix version 2.4)

Jira total went from 39 to 30 tickets.

Change

Tickets

What was done on this page

Removed from fix version 2.4

STOP-163 (HoF alert, was Pending QA), 164 (anthropometry screen), 252 (performance testing), 433 (Examine button state), 502 (card count glitch), 523 (incremental sync), 556 (toast count and colour), 557 (blank district/block/village), 580 (MDM production builds)

Moved to the "Removed from 2.4" table. Several of these were Highest or High priority, so please confirm where they went (open question 16).

Newly Closed

STOP-564 (local environment setup)

Moved to the Closed table.

Assignee changed in Jira

STOP-600, 602, 618, 619 (Contact Tracing) now with Deepak. STOP-603, 604, 620 (TPT) remain with Ashutosh.

Page now follows Jira for the mobile owners (see "Team input" below).

Priority changed in Jira

STOP-607 (button overlap) Low to High. STOP-491 (ID generator soft launch) Low to Medium.

Updated in the ticket tables.

Earlier changes (previous syncs): 12 tickets left the release (STOP-136, 182, 386, 509, 524 in the second last sync; STOP-144, 165, 171, 243, 408, 581, 583 before that). STOP-506 and 628 were closed; STOP-404 moved to Pending QA; STOP-603 moved to In Development.

Team input applied to the proposal

  • Puneet Sharma is a mobile developer and part of the delivery team. He keeps STOP-414 and STOP-599 and picks up STOP-606.

  • Mobile owners follow Jira: Contact Tracing with Deepak; TPT with Ashutosh.

  • TPT backend goes to a Backend developer:Chetan owns the TPT backend work for STOP-603, 604 and 620, with Vanitha supporting on APIs. Please confirm this alongside Ashutosh's mobile ownership (open question 17).

  • To fit the 2-week window, two splits are proposed: STOP-620 (the largest TPT ticket) to Rohit, and STOP-618 (the largest Contact Tracing ticket) to Ankit. Both can be reversed if you prefer to keep the Jira assignee.

Release priorities

Priority focus for this release, in order:

  1. TPT module improvements – STOP-603, 604, 620

  2. Contact Tracing module improvements – STOP-602, 618, 619 (plus the related Confirmed TB follow-up change STOP-600)

  3. Inventory module – additional fields – STOP-623 (BRD is a draft; see below)

  4. Nikshay enrollment and test addition – BRD is a draft; no Jira tickets yet

  5. Microplanning – no requirements or tickets yet

  6. Wrong-password attempts counter on login – STOP-599

  7. Dashboard change – STOP-606

  8. Everything else – registration and location capture, referrals and counselling, bug fixes, platform tasks (sections F to I below)

Release window plan: 26-Oct to 7-Nov-2026

What exists for the new priorities

Area

What was found

Gap

Inventory

AMRIT - Inventory Management BRD, v0.1 Draft, Pranoti Monde, updated 6-Oct. Covers Admin Portal changes only: Item Master changes, new Device Master, Device Inventory, Device AMC/Warranty and Device-to-Camp/Store mapping.

Camp-laptop sync and backend APIs are named in the purpose but not detailed. STOP-623 has no description and is not linked to this BRD. Not approved.

Nikshay

Nikshay Enrollment and Test Addition Flow BRD, v1.0 Draft, Ganesh Shirpure, 7-Oct. 15 requirements: three new MMU tabs (Generate Ni-kshay ID, Add/Update Test Results, Transfer Out), X-ray and NAAT result push, validations, sync status, admin configuration.

Not approved. Several points are marked "to confirm". The programme team still has to fill the configuration tables (PPSA ID, device PHIs, village mapping). No Jira tickets except STOP-284 (Nikshay ID POC, Highest, no fix version). Earlier Nikshay work (ID generator app, API contract) from 2.2 can be reused.

Microplanning

Nothing found for TB in Jira or Confluence (only unrelated FLW micro birth plan items).

No BRD and no UAT tickets logged.

Tracks in the window

Track

Goal in the window

Scope

A. Build and ship

Priority build

TPT (603, 604, 620), Contact Tracing (600, 602, 618, 619), login attempts (599), location capture in development (414), critical bugs (576, 449), items already in QA (404, 552, 553, 593), small UI items (504, 607)

B. Inventory

Phase 1 only if scope is approved

Admin Portal masters from the BRD (Item Master changes, Device Master, Device Inventory). Camp sync and mobile come later. Owner: Sehjot (Backend/Admin Portal); mobile developer to be named once scope is signed off.

C. Nikshay

Get ready, then build a thin slice

BRD sign-off, programme configuration data, API check (STOP-284). If approved by 28-Oct, start Tab 1 (Generate Ni-kshay ID), likely with Rohit, who did the earlier Nikshay integration. Full scope is a later release.

D. Microplanning

Discovery and UAT capture

BSAs and Product log UAT findings and requirements as Jira tickets by 30-Oct so they can be estimated. Goes into a later release.

Commit, stretch and next release

Tier

Tickets

Commit (26-Oct to 6-Nov)

TPT: 603, 604, 620. Contact Tracing: 600, 602, 618, 619. Login: 599. Bugs: 576, 449. In development: 414. Already in QA or dev complete: 404, 552, 553, 593. Small UI: 504, 607.

Stretch

606 (Dashboard, needs clarifications), 528 (Liquid Culture referral), 623 (Inventory phase 1, only if the BRD scope is signed off by 28-Oct)

Next release

412 (blocked: depends on village master data in STOP-509, which left 2.4), 491 (ID generator soft launch), Nikshay build beyond Tab 1, Microplanning, and the 21 tickets removed from 2.4

Gates and dates

Date

Gate

Owner

By Fri 23-Oct

Open questions answered: TPT (604: 5 questions, 620: 4 questions), Surveillance Officer role (619), lockout rule (599), Household screen (618)

Shivani / Vanshika / Madhava

By Fri 23-Oct

Confirm 603 hand-over and the TPT owner split

Mithun / Rupesh

Mon 26-Oct

Kickoff, scope frozen, owners confirmed, each developer and QA gives ticket estimates on day 1

Rupesh

Wed 28-Oct

Inventory and Nikshay scope signed off with estimates, otherwise moved to the next release

Shivani / Mithun

Fri 30-Oct

Microplanning UAT findings logged as tickets

Madhava / Vanshika

Wed 4-Nov

Code freeze, regression starts

Mithun / QA

Fri 6-Nov

UAT sign-off and release candidate build (target)

Rupesh / Shivani

Sat 7-Nov

Buffer; no release planned on the Diwali weekend

–

Risk to the date: if the TPT questions are not closed before 26-Oct, or if QA cannot keep pace, the realistic release candidate moves out by about 1–2 weeks, to roughly 13–20 Nov (TBD). Festival days in the week of 9-Nov will reduce availability.

Team and roles

Role

People

Mobile developers

Rohit, Deepak, Ankit, Ashutosh, Puneet

Backend developers

Sehjot, Vishwa, Chetan

API developer

Vanitha

UI developer

Sneha

QA

Deepshika, Brijesh

Delivery Manager

Rupesh

Product Manager

Shivani

Engineering

Mithun

BSA

Madhava, Vanshika

Senior Manager

Syed

How to read the ticket tables

  • Current Jira assignee shows who the ticket is assigned to in Jira today. Proposed dev owner(s) shows who should own it based on the roles above, the kind of work and the 2-week window. Jira has not been changed by this page.

  • Tickets currently held by Rupesh or Syed (not delivery developers) have been re-proposed to the right developer.

  • No effort estimates are included because the team has not estimated individual tickets yet. The allocation and load below are based on ticket counts and kind of work and are deliberately approximate.

  • Sneha is assumed to own pure UI/layout/copy changes; mobile developers own app logic.

  • Public holidays and planned leave are not yet deducted (Diwali around 8-Nov-2026; to be confirmed against the company holiday calendar).

Scope by theme

A. P0 – TPT module (Mobile and Backend)

Ticket

Summary

Jira priority

Jira status

Current Jira assignee

Proposed dev owner(s)

QA

Notes / dependencies

STOP-603

TPT follow-up: remove "Adherence to Medicines", rename ADR to "Side effects"

Highest

In Development

Ashutosh

Ashutosh (Mobile), Chetan (Backend), Vanitha (API support)

Deepshika

Already in development under Ashutosh. Build together with 600 and 604. Old records must still display.

STOP-604

TPT follow-up: replace outcome status options; "Other" becomes optional Remarks

Highest

Todo/Open

Ashutosh

Ashutosh (Mobile), Chetan (Backend), Vanitha (API support)

Deepshika

5 open clarifications (outcome mapping, date rules, removed "Developed active TB" redirect, Remarks limit, migration of old values). Blocks start.

STOP-620

TPT: "Start TPT" and "TPT Follow Up" buttons, 6 regimens, first-visit details in follow-up

Highest

Todo/Open

Ashutosh

Rohit (Mobile), Chetan (Backend), Vanitha (API support)

Deepshika

Largest TPT ticket; split to Rohit to fit the window (Jira has it with Ashutosh). 4 open questions (regimen month mapping, 250–500 words rule, default instruction text, follow-up gating).

B. P0 – Contact Tracing module (Deepak and Ankit)

Ticket

Summary

Jira priority

Jira status

Current Jira assignee

Proposed dev owner(s)

QA

Notes / dependencies

STOP-618

Add "Household" option, view/edit/update after submit, "Any other Significant Information" (500 words)

Highest

Todo/Open

Deepak

Ankit (Mobile), Vishwa (API)

Brijesh

Largest Contact Tracing ticket; split to Ankit to fit the window. Open question: should Household reuse the existing Members screen?

STOP-602

HHC tracing follow-up: Referred to = PHI / TB Camp, Remarks, auto Date, "Recommend for ATT Treatment"

Medium

Todo/Open

Deepak

Deepak (Mobile), Vishwa (API)

Brijesh

Jira assignee matches. Test both Counsellor and Surveillance Officer roles. Old referral values (TU/DH/CHC/PHC, DOTS) must still display.

STOP-619

Enable household-member "follow-up" button for Surveillance Officer role

Highest

Todo/Open

Deepak

Deepak (Mobile)

Brijesh

Jira assignee matches. Blocker question: "Surveillance Officer" is not in PRD roles. Does the role exist in the app or must it be created?

STOP-600

Confirmed TB follow-up: rename title, remove "Adherence to Medicines", ADR to "Side Effects"

Medium

Todo/Open

Deepak

Deepak (Mobile), Vishwa (API)

Deepshika

Jira assignee matches. Keep labels consistent with 603.

C. P0 – Inventory module (Track B)

Ticket

Summary

Jira priority

Jira status

Current Jira assignee

Proposed dev owner(s)

QA

Notes / dependencies

STOP-623

Additional Improvements in Inventory Modules (additional fields)

Highest

Todo/Open

Rupesh

Sehjot (Backend / Admin Portal); mobile developer TBD once scope is signed off

Brijesh

Ticket has no description. A draft BRD exists (v0.1, Admin Portal only, see "What exists" above) but is not linked or approved. Scope and size unknown. Stretch for this window.

D. Login: wrong-password attempts

Ticket

Summary

Jira priority

Jira status

Current Jira assignee

Proposed dev owner(s)

QA

Notes / dependencies

STOP-599

Wrong-password error should show remaining attempts (max 5)

High

Todo/Open

Puneet Sharma

Puneet (Mobile), Vanitha (API)

Deepshika

No change on the mobile side. Lockout message after attempt 5 is still TBD. Decide whether to show attempts for a non-existent username (security). Backend must expose remaining count.

E. Dashboard

Ticket

Summary

Jira priority

Jira status

Current Jira assignee

Proposed dev owner(s)

QA

Notes / dependencies

STOP-606

Screening Coverage Summary: "Total Eligible Population for TB Screening" with demographic breakdown

Low

Todo/Open

Rupesh

Puneet (Mobile), Vishwa (API)

Deepshika

Stretch for this window. 3 open clarifications (definition of eligible population, filter rule, replace or sit alongside STOP-500 breakdown). Depends on STOP-500 (2.3).

F. Registration and location capture

Ticket

Summary

Jira priority

Jira status

Current Jira assignee

Proposed dev owner(s)

QA

Notes / dependencies

STOP-412

Pincode and Residential Area captured once per village (supersedes GPS approach STOP-308)

Highest

Todo/Open

Sehjot

Rohit (Mobile), Sehjot (API)

Deepshika

Blocked: depends on village master PIN data (STOP-509), which left 2.4. Not in the window commit; next release unless the data source is confirmed (open question 9).

STOP-404

Auto-select "Elderly" (60+) and "Urban Slum" in Key Population / Risk Factors

Medium

Pending QA

Deepak

Dev complete (Deepak)

Brijesh

Development done. Urban Slum rule needs Residential Area from 412, so full verification may wait for 412.

STOP-414

Location capture changes (Digipin only, progress bar, edit location)

High

In Development

Puneet Sharma

Puneet (Mobile), Sehjot (API)

Brijesh

No change; stays with Puneet.

G. Referrals, counselling and TrueNat

Ticket

Summary

Jira priority

Jira status

Current Jira assignee

Proposed dev owner(s)

QA

Notes / dependencies

STOP-576

New TB Screening questions: Abnormal functionality not showing in 2.3.25

Highest

Todo/Open

Ankit

Ankit (Mobile)

Brijesh

No change. Regression from 2.3.25; fix early.

STOP-528

Beneficiary not moving to Liquid Culture referral card

High

Todo/Open

Ankit

Ankit (Mobile)

Brijesh

No change. Stretch for this window.

STOP-504

NPY and DOTS helper text in Counselling Section C

Medium

Analysis

Sehjot

Sneha (UI)

Brijesh

Copy/helper text is a UI task, not backend. Hindi translation must be provided by Product before release.

STOP-552

TrueNat: close test order when test not conducted

Low

Pending QA

Brijesh

Dev complete

Brijesh

STOP-553

TrueNat: auto-close open orders at EoD

Low

Pending QA

Brijesh

Dev complete

Brijesh

H. Bugs and stability

Ticket

Summary

Jira priority

Jira status

Current Jira assignee

Proposed dev owner(s)

QA

Notes / dependencies

STOP-449

Android Wi-Fi captive-portal check disconnects on networks without internet validation

Highest

Todo/Open

Syed

Rohit (Mobile)

Deepshika

Android-level bug, so a mobile developer. Needs device/network setup for testing.

STOP-607

OK / Cancel buttons overlap in Chief Complaint popup

High (was Low)

Todo/Open

Ankit

Sneha (UI)

Brijesh

Layout-only fix, moved to Sneha. Priority raised in Jira.

STOP-593

Default UAT URL for Connect Camp Hub in UAT build

High

Pending QA

Brijesh

Dev complete

Brijesh

I. Platform and DevOps

Ticket

Summary

Jira priority

Jira status

Current Jira assignee

Proposed dev owner(s)

QA

Notes / dependencies

STOP-491

Soft launch ID generator on 2 camp laptops

Medium (was Low)

Todo/Open

Syed

Chetan, Syed to coordinate

Brijesh

Next release.

J. Closed in 2.4

Ticket

Summary

Last Jira assignee

Note

STOP-308

PIN code and address via GPS

Agraj Parashar

Closed; superseded by STOP-412 (GPS unworkable offline).

STOP-351

Search bars in ADR (treatment follow-up, TPT follow-up) and Key population / risk factors

Shivani

Closed

STOP-397

Duplicate work orders / duplicate names on TrueNat

Sehjot

Closed

STOP-460

Optimise beneficiary photo size to prevent sync failures

Rohit

Closed

STOP-506

Add "Clinical Assessment and Diagnosis" referral queue

Shivani

Closed

STOP-564

Local environment setup on Deepsikha's and Pratiksha's laptops

Rupesh

Newly Closed since last sync.

STOP-582

House ownership radio button (Rented / Owned)

Ashutosh

Closed

STOP-628

TB Screening form takes excessively long to load

Ashutosh

Closed

K. Removed from 2.4

These tickets are no longer in the Jira fix version 2.4. Please confirm the release they moved to.

Ticket

Summary

Last known Jira assignee

Removed in

STOP-163

"Add HoF member" alert; HoF icon on card (was Pending QA)

Rohit

Latest sync

STOP-164

Anthropometry screen changes

Agraj Parashar

Latest sync

STOP-252

Performance testing of STOP_TB (reopened)

Sehjot

Latest sync

STOP-433

Examine button state reflects complete form submission

Ashutosh

Latest sync

STOP-502

Card counts (All HH / All Beneficiary / Non-Household) fluctuating

Ashutosh

Latest sync

STOP-523

Incremental beneficiary sync for large datasets

Rohit

Latest sync

STOP-556

Wrong toast count for registered family members; inconsistent colour

Ashutosh

Latest sync

STOP-557

District, Block and Village names blank for 222 records

Vishwa

Latest sync

STOP-580

Push production builds via MDM (Intune); sunset Play Store releases

Agraj Parashar

Latest sync

STOP-136

ABDM M2 Phase 1 – General OPD flow

Rohit

Previous sync

STOP-182

"Yes" button not clickable for ABHA card download

Deepshika

Previous sync

STOP-386

Unable to create ABHA on Play Store build

Deepshika

Previous sync

STOP-509

Populate village master with PIN codes

Puneet Sharma

Previous sync

STOP-524

ABHA screen UI breaks on tablet; consent text layout

Rupesh

Previous sync

STOP-144

Handling locked-door cases in HH enumeration

Puneet Sharma

Earlier sync

STOP-165

Mobile number checkbox in HH registration

Ashutosh

Earlier sync

STOP-171

Village name as default address

Ankit

Earlier sync

STOP-243

Create ABHA using Face authentication

Rohit

Earlier sync

STOP-408

Auto population of mobile number from HH registration

Rohit

Earlier sync

STOP-581

Update "Type of House" options

Rupesh

Earlier sync

STOP-583

Update "Primary source of fuel used for cooking" options

Rupesh

Earlier sync

Proposed allocation and load summary (approximate, TBD)

One view of the complete allocation for the 26-Oct to 6-Nov window (10 working days). "Tickets" counts every open ticket a person is involved in (where two people share a ticket, it counts for both, so the column adds up to more than the 22 open tickets). Closed and removed tickets are excluded. "Load" is relative to what one person can reasonably deliver in 10 working days after normal overheads (meetings, reviews, bug-fixing, support), counting only the commit and stretch scope above. It is not based on ticket-level estimates, which the team has not provided yet.

Person

Role

No. of tickets

Tickets

Kind of work

Approx. load in the window

Ashutosh

Mobile

2

STOP-603, 604

TPT follow-up forms (medium to large, blocked by open questions)

Medium (~75%); spare capacity can take STOP-528 or 576

Rohit

Mobile

3

STOP-620, 449, 412

Largest TPT ticket, an Android-level bug; 412 is blocked

Full to over (~110%); would be higher if 412 is unblocked

Deepak

Mobile

4

STOP-600, 602, 619, 404 (Pending QA)

Contact Tracing follow-up changes (small to medium)

Full (~95%)

Ankit

Mobile

3

STOP-618, 576, 528

Largest Contact Tracing ticket, Highest-priority screening bug, referral bug (stretch)

Over (~110–130%)

Puneet

Mobile

3

STOP-414, 599, 606

Location capture (in development), login change, dashboard (stretch)

Full (~95–115%)

Chetan

Backend (TPT owner)

4

STOP-603, 604, 620, 491

TPT backend for all three TPT tickets, ID generator rollout (next release)

Medium-high (~65–75%)

Vanitha

API

4

STOP-599, 603, 604, 620

Login attempt count, API support on TPT

Low (~35–40%)

Vishwa

Backend

4

STOP-600, 602, 618, 606

Contact Tracing API changes, dashboard queries

Medium (~55–65%)

Sehjot

Backend / Admin Portal

3

STOP-412, 414, 623

Location API, Inventory Admin Portal phase 1 (conditional on BRD sign-off)

Low-medium (~35–50%); headroom for Inventory and Nikshay API

Sneha

UI

2

STOP-504, 607

Small copy and layout fixes

Low (~25–30%); can also design TPT and Contact Tracing screens, and Inventory admin screens

Deepshika

QA

8

STOP-412, 449, 599, 600, 603, 604, 606, 620

TPT forms, login, Contact Tracing follow-up, Android bug

Over-allocated (~170–200%) with regression

Brijesh

QA

14

STOP-404, 414, 491, 504, 528, 552, 553, 576, 593, 602, 607, 618, 619, 623

Contact Tracing, location capture, referrals, TrueNat, small verifications, Inventory

Over-allocated (~200–230%) with regression

Key observation: mobile developers are roughly full for the 2-week window, and QA is far above what two testers can verify in 10 working days. QA is the bottleneck. To protect 6-Nov, use rolling QA from day 1, developer self-testing on small items, and BSA-led UAT (Madhava, Vanshika). If QA still cannot keep up, the date moves rather than quality being cut.

Tickets moving away from their current Jira assignee

Current Jira assignee

Open tickets held today

Moving to

Rupesh (Delivery Manager)

2

STOP-623 to Sehjot (with a mobile developer TBD); STOP-606 to Puneet

Syed (Senior Manager)

2

STOP-449 to Rohit; STOP-491 to Chetan

Developers, moved to match the kind of work or to fit the window

5

STOP-620 (Ashutosh to Rohit); STOP-618 (Deepak to Ankit); STOP-504 (Sehjot to Sneha); STOP-607 (Ankit to Sneha); STOP-412 (Sehjot to Rohit for the app side, Sehjot keeps API)

TPT backend (Chetan, Vanitha)

3

STOP-603, 604, 620 keep their mobile owners and gain a Backend owner

STOP-600, 602 and 619 (Deepak) and STOP-603, 604 (Ashutosh) match Jira. STOP-414 and 599 stay with Puneet.

Open questions and blockers

#

Item

Needed from

Affects

1

Confirm the 26-Oct to 6-Nov window and the commit / stretch / next-release split above. Accept that Inventory, Nikshay and Microplanning are readiness tracks in this window, not full builds.

Rupesh / Shivani / Mithun / Syed

Entire release plan

2

Inventory: approve the draft BRD (v0.1, Admin Portal only), decide the phase 1 scope, link it to STOP-623 and add a description to the ticket. Camp sync and mobile parts are not yet specified.

Shivani / Pranoti Monde / Madhava

STOP-623, Track B

3

Nikshay: review and approve the draft BRD (v1.0), close the "to confirm" points, get the programme team to fill the configuration tables (PPSA ID, device PHIs, village mapping), and create Jira tickets from the 15 requirements.

Shivani / Ganesh Shirpure / Programme team

Track C, STOP-284

4

Microplanning: no BRD or tickets found. Is it already built and awaiting UAT, or not yet specified? Log UAT findings as Jira tickets by 30-Oct.

Shivani / Madhava / Vanshika

Track D

5

TPT outcome clarifications (5 questions)

Shivani / Vanshika

STOP-604

6

TPT regimen mapping, "250–500 words" rule, default instruction text, Follow-up gating (4 questions)

Shivani

STOP-620

7

Does the "Surveillance Officer" role exist in the app? What else can it access?

Shivani / Madhava

STOP-619

8

Household option: same Members screen or new form? Eligible population definition for the dashboard (3 questions)? Lockout message after the 5th wrong attempt, and show attempts for unknown usernames?

Shivani / Vanshika / Engineering

STOP-618, 606, 599

9

STOP-509 (village master PIN codes) has left 2.4, but STOP-412 depends on it. Which release does 509 go to, and is 412 deliverable?

Product / Data team / Rupesh

STOP-412, 404

10

Hindi translation of NPY / DOTS helper text

Product

STOP-504

11

Ticket-level estimates from each developer and QA, on day 1 of the window

Each team member

Allocation and dates

12

Update Jira assignees to match this page once the proposal is agreed

Rupesh

All

13

Leave and public-holiday calendar for 26-Oct to end of November, including the Diwali week

Rupesh

All dates

14

Can QA capacity be increased (extra tester, BSA-led UAT, developers self-testing small UI tickets)?

Rupesh / Mithun

QA timeline

15

Confirm the TPT split: Ashutosh (603, 604) and Rohit (620) on mobile, Chetan on backend, Vanitha supporting. STOP-603 is already In Development under Ashutosh. Also confirm the Contact Tracing split: Deepak (600, 602, 619) and Ankit (618).

Mithun / Rupesh

STOP-603, 604, 620, 618

16

Which release did the 21 removed tickets move to? In particular the Highest/High items STOP-502, 557, 523, 580, 252 and the whole ABHA/ABDM block. Is any of it meant to be pulled back?

Shivani / Rupesh

Scope and allocation

Risks

  • QA capacity is far above what two testers can cover in 10 working days. Mitigations are in open question 14.

  • TPT and Contact Tracing are blocked by unresolved PRD questions. Highest-priority tickets (604, 619, 620) still have open clarifications; if they are not closed before 26-Oct, the date slips.

  • Inventory and Nikshay have only draft BRDs. Neither has approved scope or Jira tickets, so neither can be committed in the window. Nikshay also depends on the programme team providing configuration data.

  • Microplanning has no requirements at all. It cannot be planned until UAT findings are logged as tickets.

  • STOP-412 depends on STOP-509, which has left 2.4 (open question 9).

  • Large tickets in the commit scope (STOP-618, 620, 414) are already split or in development; any slippage lands on the 6-Nov date.

  • Scope is still moving (21 tickets removed and 8 closed across the last three syncs), so allocation and dates may change again.

  • Festival period: Diwali around 8-Nov. A release candidate that slips past 6-Nov is likely to land around 13–20 Nov.

Review and sign-off

Name

Role

Sign-off

Rupesh

Delivery Manager

Shivani

Product Manager

Madhava

BSA

Vanshika

BSA

Mithun

Engineering

Syed

Senior Manager