📊 Sprint Summary

  • Total Tickets in Sprint: 50

  • Tickets Completed: 29

  • Tickets Not Completed: 21


🚀 Release
As part of Sprint 40, we successfully released the following versions to production:

  • Web Application: Version 3.2.0

  • Mobile Application: Version 2.3


Thanks to everyone who contributed toward making this release smooth and on time!
⚙️ Team Velocity

  • Velocity This Sprint: 29 tickets

  • Approx. Daily Throughput: ~2.9 tickets/day

🧾 Sprint 40 Retrospective Report
The retrospective discussion and notes have been documented in Confluence.
https://pmp.piramalswasthya.org/confluence/x/5QF9BQ

🔧 Action Items for Sprint 41

  • Backend tasks to be properly tracked in Jira or discussed during 1:1s.

  • Improve coordination between planning and QA execution.

  • Limit mid-sprint ticket additions to maintain stability.

  • Estimate tickets only until Wednesday to reserve 2 days for production or regression issues.

🙏 Closing Thoughts
This was one of our better sprints — smoother execution, quicker closures, and good collaboration across the board. Several developers mentioned that this was one of the smoothest deployments in recent cycles. A few tweaks ahead, but great energy overall. Let’s aim to carry this rhythm into Sprint 41.

  • No labels