📊 Sprint Summary
Total Tickets in Sprint: 50
Tickets Completed: 29
Tickets Not Completed: 21
🚀 Release
As part of Sprint 40, we successfully released the following versions to production:
Web Application: Version 3.2.0
Mobile Application: Version 2.3
Thanks to everyone who contributed toward making this release smooth and on time!
⚙️ Team Velocity
Velocity This Sprint: 29 tickets
Approx. Daily Throughput: ~2.9 tickets/day
🧾 Sprint 40 Retrospective Report
The retrospective discussion and notes have been documented in Confluence.
https://pmp.piramalswasthya.org/confluence/x/5QF9BQ
🔧 Action Items for Sprint 41
Backend tasks to be properly tracked in Jira or discussed during 1:1s.
Improve coordination between planning and QA execution.
Limit mid-sprint ticket additions to maintain stability.
Estimate tickets only until Wednesday to reserve 2 days for production or regression issues.
🙏 Closing Thoughts
This was one of our better sprints — smoother execution, quicker closures, and good collaboration across the board. Several developers mentioned that this was one of the smoothest deployments in recent cycles. A few tweaks ahead, but great energy overall. Let’s aim to carry this rhythm into Sprint 41.